The construction of the new Police Station at 4 Fairgrounds Road is due to be completed by late September. The Police Department is tentatively scheduled to start the move process after Columbus Day. As of today, the building exterior is 95% finished with only exterior trim detail remaining. All of the exterior and interior masonry is completed. Site utilities and sidewalk curbing is installed and final site grading is underway. On the interior, the rough-in of plumbing and electrical has been completed. HVAC system rough-in has been delayed due to equipment shipping delays by the manufacturer, however completion of the HVAC system is due by mid August. All computer and telecommunications wiring has been completed. Interior walls and surfaces are completed and are being prepped for finish work. The elevator has been installed and is working. Finish millwork has been fabricated and is being installed as each room nears final completion. The electrician has started his finish work by installing light fixtures, switches and receptacles. The detention area is near completion, cell doors have been installed and the installation of detention fixtures is underway. Finish painting, and floor coverings are due to commence by August 1.
Ken Costello, ASLA, LEED AP
Landscape Architect/ Site Planner
Paul Dominov,RA
Project Designer
Kristen Smith
Interior Designer
Dave Morais, RA, LEED AP
Job Captain
Garcia, Galuska, Desousa, Inc.
Mechanical/Electrical/Plumbing
& Fire Protection Engineering www.g-g-d.com
Edward J. Galuska, P.E.
Carlos G. Desousa, P.E.
Chris M. Garcia, P.E.
JK Scanlan Company, Inc.
General Contractor www.jkscanlan.com
Craig Gabri, VP Projects
Tom Shevory, Asst. Project Mgr.
Michael Leone, Construction Supervisor